Case law
Search tips: "exact phrase" · -exclude · land | property · negligen* · citations like [2023] KEHC 123
Division and case type: CivilMiscellaneous Application
…Certified copies of proceedings and judgment were applied for by a letter dated July 22, 1980. Followed by several reminders.…
…Certified copies of the proceedings and the judgment were, however, applied for by letter dated July 22, 1980, signed by Messrs Wachira & company, who then acted for the respondent.…
Division and case type: CivilMiscellaneous Application
…8 of the Certificate of Delay states that time taken for the preparation and delivery of the papers was upto 19th June, 1998 as per paragraph 8 which is as follows: "The time required for preparation and delivery of the certified…
…copies of the proceedings and judgment was from 23rd March 1998 until 19th day of June 1998 that is to say 88 days."…